SaaS Cost of Delay Calculator

Put a number on what a slipped release costs, so the argument about the date stops being a matter of opinion.

What this calculates

This adds two costs together. The revenue the work would have earned during the weeks it did not exist, and the team salary spent during those weeks. It measures the revenue side over the twelve months after the original launch date, which is the window a board cares about and the window where a ramp still matters.

At typical inputs for a B2B SaaS company, a six week slip on a release expected to earn $1.2M a year, worked by a team costing $38,000 a week, costs $366,462, which is $61,077 for every week of delay.

Free No signup Built by an operator, not a vendor

Your numbers

Saved in your browser Reset to defaults

The prize

The delay

Results update as you type. Nothing is sent anywhere, the calculation runs in your browser.

Cost of this delay

Live

$366,462

$61,077 a week, across 6 weeks of slip

Revenue forgone $138,462Extra burn $228,000
Cost per day
$8,725
Worth paying to save one week
$61,077
As a share of the prize
31%

Watch

The delay now costs real money every week it continues. Compare the weekly figure against what it would cost to unblock the team. If a contractor, a bought component or a cut in scope costs less than one week of this, that trade is already worth making.

Pressure-test this against your real numbers

Thirty minutes on why the date slipped and what actually changes it.

Book a 30-min session

No email required to see your result. The field above exists only if you want a copy.

How is this calculated?

Two costs, added. The first is revenue you never earn because the feature arrived late, measured week by week across the year after the original launch date with the adoption ramp applied to both the on-time and the delayed case. The second is the team salary spent during the delay itself. Both are real, and most arguments about dates only count the second one.

Formula

ramp(w) = min(1, w ÷ (ramp months × 4.345)) Revenue forgone = Σw=1..52 (ramp(w) − ramp(w − delay)) × (annual revenue ÷ 52) Extra burn = team cost per week × weeks of delay Cost of delay = revenue forgone + extra burn Cost per day divides the total by seven times the weeks of delay.

When this number misleads

This assumes the revenue was going to arrive at all. If the feature was going to earn less than you projected, the delay cost falls in exact proportion, and the honest answer is that the estimate was the problem rather than the date. Run the number twice, once with your forecast and once with half of it. If the decision changes between the two, you are arguing about a forecast, not about a delay.

Questions founders ask about this

Is the team cost really a cost of the delay?

Yes, because that team could have been on the next thing. The salary is spent either way, but during a delay you are buying weeks of work that produce nothing shippable. That is the part most people leave out of the conversation.

Why does the ramp change the answer?

Because a delay pushes the whole adoption curve back, not just the first month. If it takes three months to reach full run rate, the weeks you lose are early low-revenue weeks and the effect is smaller than the headline. Over a long enough horizon the ramp cancels out entirely, which is why the window here is fixed at twelve months.

What number should I take to the board?

The weekly one. A total is a number people argue with. A weekly rate is a number people act on, because it tells them what one more week of the current plan costs and what they should be willing to spend to avoid it.

Do you store what I enter?

No. The calculation runs in your browser and nothing is transmitted. Your last inputs are saved in your own browser so the page remembers them when you return. If you use the email field, only the result summary and your address are sent.

Cite this tool SaaS Cost of Delay Calculator, Sivan Kadosh, saasfractionalcpo.com/tools-for-founders/cost-of-delay-calculator/

Book a 30-minute product strategy session

Bring the release that slipped. We will work out what actually caused it and what stops it repeating.

Book a strategy session

No pitch deck. No follow-up sequence.